Pleiades is Back to Full Capacity

18 Aug, 2014

After the cooling pumps were successfully installed, and some final issues were resolved, we were able to bring all four chillers back online today. Pleiades is now back up to full capacity.

The Systems Status page may continue to show degraded capacity for a brief time, however, you can log in and submit your jobs normally.

We expect the hyperwall and the Maia and Mira test systems will also be back online soon, and will keep you informed.

We sincerely apologize for the impact this situation has had on your work, and we thank you for your patience. If you have any further concerns or issues, please contact the NAS Control Room at (800) 331-8737, (650) 604-4444, or support@nas.nasa.gov.

Contact Us

General User Assistance

Security

  • Report security issues 24x7x365
  • Toll-free: 1-877-NASA-SEC (1-877-627-2732)
  • E-mail: soc@nasa.gov

User Documentation

High-End Computing Capability (HECC) Portfolio Office

NASA High-End Computing Program

Tell Us About It

Our goal is furnish all the information you need to efficiently and effectively use the HECC resources needed for your NASA computational projects.

We welcome your input on features and topics that you would like to see included on this website.

Please send us email with your wish list and other feedback.