NAS System Status for August 15

15 Aug, 2014

The cooling tower pumps have been repaired and were installed this week. A water pipeline on one of the pumps was corroded and is now being fixed, and we are testing the cooling system components while the pipeline is repaired. We currently expect to bring Pleiades back to full capacity early next week, after testing is complete. 

Current status of NAS resources:

Pleiades Half capacity
Westmere Half
Westmere GPU  Full
Sandy Bridge Half
Ivy Bridge Half
Endeavour Full capacity
Merope Full capacity
Maia Down
Mira Down
Hyperwall Down
Filesystems Up
Archive Up

Thank you for your patience. We apologize for the impact this has on your work. If you have concerns about job processing, please contact the NAS Control Room at (800) 331-8737, (650) 604-4444, or support@nas.nasa.gov, or contact Cathy Schulbach at 650-604-3180 or catherine.h.schulbach@nasa.gov.

Contact Us

General User Assistance

Security

  • Report security issues 24x7x365
  • Toll-free: 1-877-NASA-SEC (1-877-627-2732)
  • E-mail: soc@nasa.gov

User Documentation

High-End Computing Capability (HECC) Portfolio Office

NASA High-End Computing Program

Tell Us About It

Our goal is furnish all the information you need to efficiently and effectively use the HECC resources needed for your NASA computational projects.

We welcome your input on features and topics that you would like to see included on this website.

Please send us email with your wish list and other feedback.