Pleiades to be Upgraded this Summer

01 Jul, 2013

The total computing power of Pleiades will be significantly increased this summer with the addition of 3312 Ivy Bridge nodes. To make way for the new addition, the Pleiades Harpertown nodes will be removed; and some outages will be required.

Tentative schedule for the upgrades:

  • July 15: System-wide outage to remove half (2048) of the Harpertown nodes to make room for the first batch of Ivy Bridge nodes.
  • August 5: Initial 1152 Ivy Bridge nodes become available to users. These have computing power approximately equivalent to all the 4096 nodes of Harpertowns being removed.
  • Later that week, there will be another outage to remove the remaining 2048 Harpertown nodes.
  • Aug 19: Additional 1152 Ivy Bridge nodes become available.
  • Aug 26: Final 1008 Ivy Bridge nodes come online.

If you have any questions or concerns, please contact us as soon as possible.

NAS Control Room
support@nas.nasa.gov
800-331-8737
650-604-4444

Contact Us

General User Assistance

Security

  • Report security issues 24x7x365
  • Toll-free: 1-877-NASA-SEC (1-877-627-2732)
  • E-mail: soc@nasa.gov

User Documentation

High-End Computing Capability (HECC) Portfolio Office

NASA High-End Computing Program

Tell Us About It

Our goal is furnish all the information you need to efficiently and effectively use the HECC resources needed for your NASA computational projects.

We welcome your input on features and topics that you would like to see included on this website.

Please send us email with your wish list and other feedback.